The Intensive English High School relocated to new premises on Mitchell Road, Alexandria, requiring construction to ensure the location was fit for purpose. The school, now known as Central Sydney Intensive English School, provides students with 23 specialised learning areas. The project required a new building extension constructed onsite and integrated into the existing heritage building.
This project was conducted in three stages:
Stage 1: Rectification of specific areas of a previously built building extension to correct defects and meet BCA compliance.
Stage 2: Refurbishment of the existing heritage-listed building.
Stage 3: Fit-out works for specialised learning areas.
Scope of Works: Ages Build completed the following tasks:
-
Ensuring BCA compliance for services
-
Installing wall partitioning
-
Adding acoustic wall linings
-
Updating roof flashings
-
Painting
-
Laying floor finishes
-
Creating feature artistic wall murals
-
Conducting heritage refurbishm
Project Phases and Timeline:
-
Stage 1: Completed in 22 days.
-
Stage 2: Completed in 14 days.
-
Stage 3: Completed in 15 days.
Project Highlights:
-
Efficiency: The project was executed with an accelerated timeline, achieved through careful planning, early procurement of materials, and additional after-hours work, to ensure no student learning was impacted.
-
Integration: The new facilities were seamlessly integrated with the existing heritage building.
-
Readiness: All stages were completed promptly, ensuring minimal disruption and immediate availability for students.
Ages Build successfully delivered a modern, functional, and inspiring educational environment, preserving the heritage charm while equipping the school with state-of-the-art facilities.