Northmead Capa High School
Client: NSW Department of Education
Contract Value: $2,519,388.6
Program Duration: 52 weeks
Ages Build was tasked with enhancing the sports field area at the High School, delivering a comprehensive four-stage project.
Stage 1: Basketball Court Shade Structure
-
Scope: Construct a new shade structure over two existing asphalt basketball courts.
-
Additional Work: Included plumbing and electrical upgrades.
-
Timeline: Completed within 12-18 weeks.
Stage 2: Basketball Court Resurfacing
-
Scope: Resurface two asphalt basketball courts, which involved removing old sports equipment, laying a new concrete slab, applying an acrylic court surface, and installing new sports equipment.
-
Timeline: Completed in 8 weeks.
Stage 3: Netball Court Reconstruction
-
Scope: Demolish the existing netball court surface and construct a new 100mm reinforced concrete netball court, complete with new line marking and an ag-line drainage system connecting to the stormwater pit.
-
Timeline: Completed in 2-4 weeks.
Stage 4: All-Weather Sports Structure
-
Scope: Construct a large all-weather structure featuring a concrete futsal/netball court with a synthetic turf surface, line markings for two futsal and two netball courts, stormwater drainage, new sports equipment, and ball protection netting.
-
Timeline: Completed within 16-24 weeks.
Project Highlights:
-
Minimised Disruption: All work was carried out during school holidays and within an active school environment, ensuring minimal impact on daily school activities and exams.
-
Safety and Timeliness: The project was completed on time and without any incidents.
Ages Build successfully transformed the sports facilities, providing the school with modern, functional, and safe sports areas for students to enjoy.